2011-12-29 04:58:39 (10933 views) DreamLover 2000 units should be ready to ship from our UK warehouse within 5 days.
We're trying to hurry up with the US shipment too but it may take a few days longer.
ChronoVaults will still require some time - all electronic and mechanical components are ready, but we're having to make more mold modifications to the exterior in order to get the best possible result.
2011-12-21 07:07:36 (10811 views) 3 full days of FIRE at the factory and untold difficulties but the boards are ready to be sent in the next few days after another few rounds of testing.
2011-12-18 03:47:19 (11496 views) Several mold changes and 3 vendors later (the first two quit after taking a deposit because the job was too difficult), we now have an improved and strengthened ChronoVault. The top part has overmolded metallic parts.
Maximum quality and seriousness about your male's orgasm reduction, it's how we do things at DreamLover Labs.

2011-12-15 08:00:25 (11888 views) After untold problems clearing components from customs, yesterday we showed up at the factory 3 hours away only to find they had "misplaced" the stencil and that we had to come back again the next day. Today though, finally we have some great results.
This new assembly house does not have all the fancy tools the other one had, but they work HARD. There were a few critical moments that required our presence (capacitors mounted the wrong way, boards falling off the conveyor belt because no one was there to pick them up after going through the oven, one accelerometer that needed further soldering) but today we put together 5 beautiful and perfectly working ChronoVaults, 5 DreamLover 2000 receivers and 5 remote controls. We've befriended the boss and she's now personally mounting components for us and looking over a few helpers. She's very skilled and on top of things, so we'll just stay home and let them work. This assembly house has a high percentage of female workers. One of them, who is doing most of the ChronoVault work, is very cute and has beautiful slim hands capably handling our components and freshly built boards.
We should have everything finished up by Monday or Tuesday, so we'll go back to the factory to test everything, make any necessary adjustments, and hopefully ship everything to our warehouses ready for your last-minute Christmas orders!
2011-12-12 00:34:24 (10043 views) Should be delivered tomorrow with "only" 5 days delay.
Hopefully we can assemble on Dec 14th and send some product to our warehouses with enough days left before Christmas to take some orders.
2011-12-09 09:50:32 (12501 views) One DreamLover 2000 Pilot Run user from Canada has submitted the results of his work on a PA5000 + DreamLover 2000 prototype. Note the well shaped and very smooth custom electrode he has built.

This is the 3rd user adaptation for devices we never planned on supporting... after the Latowski + DreamLover 2000 combo from a client in Germany and Q's notorious adaptation of MatureMetal's devices which can now be ordered directly from MatureMetal.
|